Building certainty: the priority in UAE developments  | Corbis: News & Agenda

Strong pipelines, growing market confidence, and an ultra-luxury segment that's beginning to make room for affordable luxury. As project volumes increase and timelines accelerate, Design Coordination becomes even more crucial to support efficient delivery. Here are the takeaways from our last client visits.

UAE market outlook for the coming months is positive, ambitious, and shows a stronger focus on execution, with expectations of an even faster pace going into 2027. Conversations are more pragmatic, with greater attention on how to deliver efficiently while ensuring quality across complex, large-scale projects.

We also see broader diversification in the luxury residential market. Ultra-luxury remains relevant, while other segments, like affordable luxury, gain importance and take a larger share of development activity, reaching a broader customer base.

Against this backdrop, developers' priorities in the region are: 

# Deliver the current pipeline while preparing for expanding project volume. 

# Maintain design quality while improving cost and schedule efficiency. 

# Strengthen delivery structures and technical capacity without unnecessary growth. 

In other words: scalability and predictability, not just more projects.

Mariana Marchesse, our Business Development Executive, came back home with clear, motivating insights after visiting clients and construction sites in the United Arab Emirates.

Recurring risks to keep an eye on 

A persistent challenge is that too many design and coordination issues are still being resolved during construction. In some cases, changes continue even into the as-built stage. From a developer's perspective, this reduces predictability and can translate into RFIs, variations, rework, late decisions, additional costs, and schedule impacts. As project volumes and delivery speeds increase, this risk grows even greater. 

The recurring theme is that the market's scale and speed are increasing pressure on project delivery. At the same time, unresolved design issues still tend to move downstream into construction. This creates a clear need for greater design maturity before construction and stronger alignment between consultants, disciplines, and project stakeholders. 

Many developers already have strong internal design teams, so the opportunity is not simply to provide additional resources. The greater value is in helping them identify unresolved interfaces, challenge design information across disciplines, and close coordination issues before they reach construction. 

From the developer's perspective, the objective is simple:

Resolve issues while they are still design decisions, before they become construction problems.

That's exactly what our Design Coordination delivers in the early stages of the project, directly impacting cost, schedule, and coordination certainty from day one.